Pune Makes 980 MLD of Sewage but Treats Only 591 MLD: Union Minister Reviews Mula-Mutha Cleanup; STPs Due by March 2027
Pune treats only about 60% of the 980 MLD of sewage it makes. Union Minister C R Patil reviewed the Mula-Mutha cleanup and new STPs due by March 2027.

Photo: Rsrikanth05 / CC BY-SA 4.0, via Wikimedia Commons
Pune, 22nd November 2026: Pune generates about 980 million litres of sewage a day (MLD), but the Pune Municipal Corporation (PMC) can treat only about 591 MLD, or roughly 60%, according to figures shared at a review of the Mula-Mutha cleanup project. The rest of the untreated sewage is a key reason the rivers stay polluted.
Union Jal Shakti Minister C R Patil reviewed the project at the Central Water and Power Research Station in Khadakwasla on Thursday, 19 November.
What the review covered
The meeting reviewed the Pollution Abatement of River Mula-Mutha at Pune project, under the National River Conservation Plan, Punekar News reported. Union ministers of state Murlidhar Mohol and Dr Raj Bhushan Choudhary, Mayor Manjusha Nagpure and Municipal Commissioner Naval Kishore Ram attended, along with central and PMC officials.
Status of new sewage treatment plants
- 11 sewage treatment plants (STPs) with a combined capacity of 396 MLD are being built under the project.
- Five plants, with 111 MLD, are complete.
- All plants except the one at Botanical Garden are due by March 2027.
- The sewerage network linked to them is expected by October 2027.
The PMC aims to add 285 MLD of treatment capacity by March 2027, and plans to generate electricity from gas engines at the Bhairoba STP.
Why the gap matters
A gap of nearly 390 MLD means hundreds of millions of litres of untreated or partly treated waste water reach the rivers and nalas every day. Even after the 11 new plants are ready, the PMC’s own figures show it will need more capacity to treat all the sewage the city produces, which is why a further expansion is already being planned.
How the rest will be funded
A further 535 MLD of capacity is planned, to be funded through the Centre’s Urban Challenge Fund, AMRUT, the hybrid annuity model and the PMC’s own funds.
What the minister asked for
- lower construction and running costs for STPs, using lessons from Namami Gange
- tender clauses for replacing and upgrading equipment over seven years
- incentives for quality and on-time completion
Patil also inspected the 26 MLD STP at Wadgaon and suggested reusing treated water for gardening and construction.
What it means for residents
Until treatment capacity catches up with sewage generation, untreated waste will keep reaching the river, and areas along the banks will keep facing smell and mosquito problems. The cleanup is separate from the riverfront beautification project, whose flood impact is being studied by CWPRS; see our CWPRS Mula-Mutha flood study report.
Frequently asked questions
How much sewage does Pune generate?
About 980 million litres a day, against a treatment capacity of about 591 MLD.
When will Pune’s new sewage plants be ready?
All plants under the Mula-Mutha project except Botanical Garden are due by March 2027, with the sewer network by October 2027.
Who reviewed the Mula-Mutha cleanup project?
Union Jal Shakti Minister C R Patil reviewed it on 19 November 2026 at CWPRS, Khadakwasla.