HCMTR Pune: PMC General Body Approves Rs 2,634 Crore Land Acquisition for 43.6-Km Elevated Ring Corridor; Route, Lanes and Next Steps
PMC approved Rs 2,634 crore to acquire land for the 43.6-km elevated HCMTR. See route areas, lane design, the 1987 history and the January target.

Photo: Amityadav8 / Public domain, via Wikimedia Commons
Pune, 21st November 2026: The Pune Municipal Corporation (PMC) general body on Friday approved a Rs 2,634 crore proposal to acquire land for the High Capacity Mass Transit Route (HCMTR), a 43.6-km elevated ring corridor around the city. The PMC will bear the full cost.
The road was first proposed in the city’s 1987 development plan, so this is one of the oldest unfinished projects in Pune.
What the general body approved
As reported by the Free Press Journal, the proposal covers about 4,98,390 square metres of land. The project as a whole needs about 144 hectares, and roughly 51% of that already belongs to the PMC.
The administration has recommended that the Standing Committee also clear the proposal before it goes to the state government. HCMTR project head Dinkar Gojare briefed the general body.
Route: which areas the HCMTR passes through
Land is to be acquired in Bopodi, Aundh, Bhamburda, Erandwane, Kothrud, Hingne, Parvati, Munjeri, Wanowrie, Hadapsar, Mundhwa, Wadgaonsheri, Lohegaon, Yerawada and Dhanori.
The corridor also passes near Harris Bridge, Swargate, Magarpatta, Viman Nagar, Vishrantwadi and Khadki. About 29 km of it runs along existing roads.
Six lanes, with two for electric buses
The design has six lanes:
- two central lanes for electric buses
- four lanes for private cars and other four-wheelers
- no access for two-wheelers and three-wheelers
There will be entry and exit ramps at 10 locations. So a driver from Kothrud heading to Viman Nagar could, in theory, use the ring corridor instead of cutting through the city centre.
How compensation will be paid
Under the 2013 land acquisition law, 30% of compensation is usually deposited before notification. The District Collector has said this is not needed at the first stage, and full compensation can be paid at the final award. Owners whose land falls on the route should keep their 7/12 extracts and property cards ready.
How the project got here
- 1987: proposed in the PMC development plan, originally about 36 km
- 2018: final alignment prepared, with changes at 12 places
- 2024: revised alignment approved by the state
- July 2026: a two-tier committee set up, led by the PMC commissioner and the Chief Minister
What happens next
The PMC wants private land acquisition finished by January. It must also get permission for Defence and Forest land, plan sound and vision barriers, and coordinate with MahaMetro and MSIDC at seven crossings. Construction will be split into four packages. No completion date has been announced.
For other big road projects, see our Pune Ring Road status update.
Frequently asked questions
What is HCMTR in Pune?
The High Capacity Mass Transit Route is a planned 43.6-km elevated ring corridor around Pune with six lanes, two of them reserved for electric buses.
Can two-wheelers use the HCMTR?
No. As per the current design, two-wheelers and three-wheelers will not be allowed on the corridor.
When will HCMTR be completed?
No completion date has been announced. The PMC aims to finish private land acquisition by January before work starts in four packages.