New Complaint ignored? Lost something in a cab? Raise it on the Punekar Help Desk and let Pune back you up. Raise it

Swargate to Katraj Metro: 5 Underground Stations, First Tunnel Boring Machine Arrives, Tunnelling From January

Where the underground Swargate to Katraj Metro stands in November 2026: the five stations, the first tunnel boring machine, traffic changes and the 2029 target.

Swargate underground Metro station in Pune, where the Katraj extension begins

Photo: DesiBoy101 / CC BY 4.0, via Wikimedia Commons

Last updated: 18 November 2026

The Swargate to Katraj Metro is a 5.46 km underground extension of Pune Metro’s Purple Line, with five stations under Satara Road. The first of four tunnel boring machines (TBMs) has reached Pune, and MahaMetro expects tunnelling to start in January 2027.

Here is where the project stands, which stations are coming and what it means for people living and travelling along the Swargate, Market Yard, Bibwewadi, Dhankawadi and Katraj stretch.

Swargate Katraj Metro stations and route

The line continues south from the existing underground Swargate station on the Pimpri Chinchwad to Swargate corridor. All five new stations are underground:

  • Market Yard (Gultekdi)
  • Bibwewadi
  • Padmavati
  • Balaji Nagar
  • Katraj

The original plan had only three stations: Market Yard, Padmavati and Katraj. Bibwewadi and Balaji Nagar were added) after public consultations, and the Centre gave final approval to the extension on 16 August 2024.

Once it opens, a rider from Katraj will be able to travel without changing trains to Swargate, Kasba Peth, Shivajinagar and on to Pimpri.

First TBM arrives: how the tunnel will be dug

Punekar News reported on 4 November that the first of four TBMs has arrived. Each machine will be assembled and lowered underground once the launching shaft at Swargate is ready.

The digging plan, as described by MahaMetro:

  • Two TBMs will start from Swargate and two from Katraj.
  • All four are expected to meet at Padmavati.
  • The tunnels will run about 28 metres below ground.
  • MahaMetro is targeting about 10 metres of tunnel a day per machine, based on its experience in the first phase.
  • Rocky ground is expected along the route.

Excavation for the launching shaft at Market Yard has also begun.

Who is building it and when will it open

ITD Cementation India emerged as the lowest bidder for the civil package covering the five underground stations and twin tunnels, at ₹1,643.88 crore, Metro Rail Today reported in September 2025. That was about 24% below MahaMetro’s estimate of ₹2,144 crore.

The contract allows 42 months, with full operations targeted for February 2029. Work is split into two stages: Market Yard, Padmavati and Katraj first, then Bibwewadi and Balaji Nagar.

Overall project cost figures differ across official documents and reports, because the estimate was revised after two stations were added. We have not quoted a single total for that reason.

Land for Padmavati station near Dhankawadi

Land is now being handed over for station sites. On 3 November, the PMC’s City Improvement Committee approved transferring 665 sq m of land in Dhankawadi to MahaMetro for Padmavati station, as we reported earlier. The proposal still needs final approval from the PMC General Body.

Traffic changes on Satara Road during construction

Metro work has already changed how buses run between Swargate and Katraj. In May 2026, Pune Metro and PMPML shifted buses out of the central BRTS lane between Morebaug and Bhapkar Petrol Pump near the Market Yard and Bibwewadi sites.

  • BRTS stops on that stretch were closed and temporary stops set up along the footpath.
  • Buses and other vehicles now share a wider common lane.
  • Towards Katraj, buses rejoin the BRTS corridor after Nathubaug bus stop.

Expect this pattern to spread to more stretches once shafts open at Padmavati, Balaji Nagar and Katraj. Leave extra time on Satara Road at peak hours.

What is still not known

MahaMetro has not announced a date for the first TBM launch beyond January, a station-wise completion schedule, or fares for the extension. Opening in February 2029 depends on tunnelling keeping pace through rock.

We will update this page as work progresses. For current Metro lines, timings and fares, see our Pune Metro timings and fares guide.

Get Pune news on WhatsAppWater cuts, traffic, Metro, events and civic updates, straight to your phone. Free, and no spam.
Join our WhatsApp Channel

Frequently asked questions

When will the Swargate to Katraj Metro start?

The contract targets full operations by February 2029. Tunnelling is expected to begin in January 2027.

What are the stations on the Swargate Katraj Metro line?

Market Yard, Bibwewadi, Padmavati, Balaji Nagar and Katraj, all underground, beyond the existing Swargate station.

Is the Swargate to Katraj Metro underground or elevated?

It is fully underground, with tunnels about 28 metres below Satara Road.

How long is the Swargate Katraj Metro line?

About 5.46 km from Swargate to Katraj.

Found this useful? Share it with a Punekar who needs it
Written by
Prashant Chaudhari
Editor, Puneri Pages

Prashant Chaudhari is the founder and editor of Puneri Pages. Based in Pimpri-Chinchwad, he oversees the site’s editorial standards and fact-checking, and writes about Pune events, civic updates, business and technology.

Punekar Help Desk
Join WhatsApp Channel