Mulshi Dam Water for Pune: CM Fadnavis Approves Extra 8 TMC; Supply Expected in 18 to 24 Months After PMC Builds Pipeline
An extra 8 TMC from Mulshi Dam is approved for Pune. PMC must prepare a DPR for a pipeline, jackwell and treatment plant; water expected in 18 to 24 months.

Photo: Abhishek Pathak / CC BY-SA 3.0, via Wikimedia Commons
Pune, 21st November 2026: Pune city has been allocated an extra 8 TMC (thousand million cubic feet) of water from Mulshi Dam, after a meeting chaired by Chief Minister Devendra Fadnavis. Municipal Commissioner Naval Kishore Ram said the water could reach the city in 18 to 24 months.
The catch: the Pune Municipal Corporation (PMC) first has to plan and build the infrastructure to bring it in. Until then, daily supply in the city depends on the same sources as before.
What has been decided
According to Punekar News, the decision was taken at a meeting chaired by the Chief Minister on Friday, 20 November. Commissioner Ram confirmed the allocation and gave a timeline of “one-and-a-half to two years”.
The Chief Minister also asked for long-term water security plans for growing cities, the Free Press Journal reported. Mulshi Dam lies west of Pune, near Paud in Mulshi taluka.
What PMC must build first
The water will not flow into taps on its own. The PMC has to prepare a detailed project report (DPR) for:
- a large pipeline from Mulshi Dam to the city
- a jackwell to lift water from the dam
- a water treatment plant
- related distribution infrastructure
No cost estimate or funding plan has been announced yet. The PMC will have to work out the money needed once the DPR is ready, and the project will then need tenders and approvals.
Why Pune needs more water
Pune draws most of its supply from the Khadakwasla dam system, whose stock is reported to be lower than last year. Demand keeps rising from Pune, Pimpri-Chinchwad and the growing PMRDA belt.
There are also worries about El Niño and a weak monsoon in parts of Maharashtra next year. The PMC is already running water conservation measures, and several areas face scheduled cuts; check our Pune water cut today page for the current schedule.
What it means for residents
For now, nothing changes in daily supply. The extra 8 TMC is a medium-term fix. If the DPR, approvals and construction move on time, the new source could help the city from 2028. Residents in fringe areas that depend on tankers are likely to watch this project most closely.
What is still not clear
- the pipeline route and which parts of Pune will be fed first
- the project cost and who will pay for it
- whether the PMC will need to pay for the water to the dam’s operator
We will update this story when the PMC releases the DPR.
Frequently asked questions
How much extra water will Pune get from Mulshi Dam?
Pune has been allocated an additional 8 TMC of water from Mulshi Dam.
When will Pune get Mulshi Dam water?
Municipal Commissioner Naval Kishore Ram said it could take 18 to 24 months, since a pipeline, jackwell and treatment plant must be built first.
Will water cuts in Pune stop now?
No. The Mulshi water is a future source. Current cuts depend on Khadakwasla storage and PMC’s schedule.